Recover a Slipping Engineering Project

MediumExecution00:00
Practice interviewer
In session
5 left
00:00

Your question is Recover a Slipping Engineering Project. Take a moment with it on the right.

Talk me through your thinking if you like. When you're confident, submit your answer and I'll grade it like a real screen (7/10 or better passes).

You need to log in / sign up to chat or submit.

Problem

Scenario

You are the Engineering Manager for a customer-facing initiative that is already 4 weeks into a 12-week plan and is now projected to miss its launch date by 3 weeks. The work touches a shared services team, a vendor integration, and a compliance review, so delays in one area are blocking the others. The product leader wants to preserve the original scope, the sales team has already committed to a launch window, and one senior engineer has raised concerns that the current plan is underestimating testing and integration work. You need to decide how to get the project back on track without creating avoidable rework or damaging trust.

Constraints

DetailValue
Planned timeline12 weeks total
Time elapsed4 weeks
Forecast slip3 weeks
Core team1 EM, 4 engineers, 1 QA, 1 product manager
External dependency1 vendor integration with weekly release windows
Compliance reviewRequired before launch
Stakeholder commitmentSales has promised a launch window to 2 enterprise customers

Question

How would you handle this project so you can recover the schedule, align stakeholders, and decide what trade-offs to make?