At DoorDash, you are the program manager for a new courier batching feature intended to reduce delivery costs in mid-sized US cities. The project team includes 6 engineers, 1 data scientist, 1 designer, 1 operations lead, and you. Leadership wants the feature launched before the start of the holiday peak, giving the team 8 weeks to decide scope, validate readiness, and execute.
The GM of Logistics wants a broad launch to hit quarterly cost targets. The Head of Merchant Experience is concerned that batching could increase delivery times and hurt merchant satisfaction. Engineering wants to avoid adding last-minute city-specific exceptions, while Finance is pushing for a launch in at least 10 cities to justify the $420K already invested.
You have a remaining execution budget of $160K, no additional headcount, and only 8 weeks before code freeze. Historical pilot data from 4 cities shows batching reduces cost per order by 6.8%, but in 2 cities it also increased late deliveries by 2.4 percentage points and lowered merchant NPS by 5 points. The routing service team can support only 3 major backend changes before freeze, and legal requires 10 business days to review any courier incentive changes.