VoltWay is a mid-sized mobility infrastructure company that operates 420 fast-charging stations across Western Europe and generated €86M in revenue last year with an EBITDA margin of 14%. The company is considering a new project: building a network of 60 ultra-fast EV charging hubs along major intercity highways in Spain. Management believes the project could strengthen VoltWay's position before larger utilities and oil majors expand further into the market, but the board wants a clear view on whether the project is financially viable before committing capital.
You are a strategy manager at VoltWay. The CEO has asked you to evaluate whether the Spain highway expansion should move forward. The decision matters now because EV adoption is accelerating, several public subsidies expire in 9 months, and two competitors have announced plans to expand on overlapping routes. Your assessment should determine not only whether the project creates value financially, but also what assumptions matter most and what commercial strategy would improve returns.
| Metric | Value |
|---|---|
| Planned sites | 60 highway charging hubs |
| Average upfront capex per site | €1.8M |
| Expected government subsidy | 20% of capex, if approved within 9 months |
| Annual fixed operating cost per site | €140K |
| Variable electricity + maintenance cost | €0.24 per kWh sold |
| Proposed average retail price | €0.46 per kWh |
| Expected year-1 volume per site | 1.4M kWh |
| Expected annual volume growth (years 2-5) | 18% |
| Corporate hurdle rate | 10% |
| Project life for evaluation | 10 years |
Additional market context: